LIXiSE LXC6120 ATS generator controller switch conversion process
LIXiSE LXC6120 ATS generator controller Switch the conversion process is divided into: manual conversion and automatic conversion process.Below we detailed to introduce the two kinds of ATS switch conversion process.
1, manual conversion process:
Generator controller In manual mode, the switch of the control process is completed by manual.Operator control through close break-brake key ATS switch load conversion.But according to different ATS switch configuration, the concrete process will have a little difference:
◆The default is not enabled in pieces break-brake detection
After the press brake power generation or points, according to the current load condition in two processes:
1, if the power is on load, brake power points;If the load is disconnected, the power switch;
2, if the mains are on load, the grid points brake, when after the break-brake time delay, power switching again;
When press the mains close break-brake button, if the mains are on load, the grid points brake;If the load is disconnected, the mains switch.If at this point is the power is on load, the power brake, when after the break-brake time delay, mains switch again.
2. The automatic conversion process:
Generator controller in manual commissioning or automatic or stop mode, the switch is the control process of automatic conversion.
◆The default is not enabled in pieces break-brake detection
1, from the utility load to power load, through break-brake time delay, after conversion interval delay, power switch, power switch starting test power switching auxiliary input at the same time, to the testing time, if the switch failure, continue to wait for power switch.At this point if the conversion can make failure warning, issued a warning signal.
2, from power generation on load to the utility belt, the above principle.